FOUNDERS HALL Construction Update

November 4, 2009

           

  • This week and next, building progress focuses on:
    • Backfilling along the south wall adjacent to the Fairfax Drive sidewalk
    • Work continues on installation of elevators #3 through #8
    • Installation of various metal structures (stairs, elevator divider beams, etc) continues
    • Continue exterior stud framing and CMU (concrete masonry unit) along the western elevation
    • Continuing framing of interior partitions-Levels 3 & 4
    • Complete metal panels along north alley and begin metal panel installation along east & west wings
    • Erect structural steel at Mezzanine and 7th floor
    • Place concrete on Mezzanine level
    • Begin erecting structural steel on main roof
    • MEP (mechanical, electrical, & plumbing) and sprinkler installation work continues
  • Two Week Look Ahead:
    • Set cooling towers, boilers, etc on Level 7
    • Work begins to bring water into building
  • 30-60 Day Look Ahead:
    • Begin storefront installation
    • Complete rooftop equipment and structural steel
    • Tie-in work to Hazel Hall late December (2nd-4th floors)
      • Lobby tie-in work delayed to spring break 2010
    • Complete rooftop structural steel mid December
    • Begin drywall installation end of December/beginning January
    • Complete auditorium roof
  • 90 Day Look Ahead:
    • Complete gas service
    • Complete metal panels through Level 5 – begin Levels 6 & 7
    • Complete structural steel for bridge to Foundation Building in January
    • Complete all stairs
  • As of this date –project is 65% completed

SPECIAL NOTES: 

  • Due to the construction, the two Hazel Hall passenger elevators have been turned off to the B-2 level. (Please call 703-338-9049 if you need access.)

PLEASE WATCH THIS SITE

Founders Hall Project updates will be posted every two weeks following construction progress meetings. 

Time sensitive and/or special alerts will be shared via the ARL Campus Information list serve.

The Founders Hall web cam can be accessed at:   http://arlington2webcam.gmu.edu/index.cgi

(Note:  a page will first come up and ask viewers to load an active-X or java application.  Choose the viewing program most appropriate for your computer.  Log-in via the provided “Guest” user name and password)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

     

 

"));